Guide · Restaurants
Custom restaurant booths: what to settle before the bid.
Booths set the layout and the look of a dining room, and they’re usually the biggest custom seating order on a restaurant job. Most surprises in price and schedule trace back to a few decisions left open when the package went out. Settle these eight first and every bid you get back prices the same booth.
1. Built-in or freestanding
Built-in booths and wall banquettes tie into the construction: they need wall blocking, finished wall caps or back panels, and a clear answer on who installs and anchors them. Freestanding booths cost less to install and can be moved for cleaning or a new layout. Decide per run, and put installation scope in writing so it isn’t split between the furniture maker and the general contractor by accident.
2. Final dimensions, from the field
Booths are built to your drawings, so the drawings must match the room. Confirm seat height, back height, seat depth and run lengths, then check run lengths against field measurements once walls are up. Ask how long runs will ship: every section has to fit through the doors, stairs and elevator on the way in, and long runs are often built in pieces. The seating standards chart has the usual booth, bar and table dimensions.
3. Accessible seating
Under the 2010 ADA Standards, at least 5 percent of seating spaces at dining surfaces must be accessible and spread through the room, with surfaces 28 to 34 inches high and knee clearance at least 27 inches high. A fixed booth rarely works for a wheelchair user, so place the accessible tables before the booth layout is final, not after.
4. Upholstery that survives service
Dining seating is heavy-duty use. The Association for Contract Textiles’ guideline for high-traffic public spaces is at least 30,000 double rubs on the Wyzenbeek test, or 40,000 cycles on the Martindale test. Check cleanability too: the fabric’s cleaning code, and whether it can take the restaurant’s cleaning products. Many dining rooms put a performance vinyl or coated fabric on the seat and a decorative fabric on the back.
5. COM yardage, settled early
If the client is supplying fabric (COM), have the maker calculate yardage from the final drawings, not from a rule of thumb. Pattern repeat, fabric width, channel tufting and whether the fabric can be railroaded (run horizontally along a long back without seams) all change the number. Add who pays freight on the COM, when it has to arrive, and whether non-contract fabric needs a backing before it can be used.
6. Flammability, confirmed locally
Contract upholstered seating is commonly built to California TB 117-2013. In Tennessee, the State Fire Marshal’s Office enforces the 2021 International Fire Code with state amendments, and some cities adopt their own editions. Ask the local fire code official what upholstered seating needs for your occupancy, and ask the maker for test documentation on the fabric and the finished piece.
7. The details that move the price
Write these into the spec so bids price the same thing:
- Back style: channel-tufted, tight back, button-tufted or plain
- Welts, contrast piping and seams
- Crumb gap or clean-out between seat and back
- Kick plates, toe kicks and base finish
- Wood or metal trim, back caps and end panels
- Power, USB or lighting built into the booth
8. A schedule built backward from opening day
Production starts only after shop drawings, finishes and fabric are approved, so late approvals are the most common cause of late booths. Work backward from the opening date: shop drawing review, finish and fabric approval, COM arrival, production, freight and installation. Ask the maker for each lead time in writing before you set the dates.